Restricting PWA user from entering more than 24h for a day for a t

F

FMCyb

We have integrated our Project 2003 server with our old web based time entry
system.

In that time entry system user can't enter more than 24 hours of work for a
day.

Here is the question:

How can we restrict a team member from entering more than 24 h of work for a
day for a single task in PWA?

Thanks
FM
 
D

Dale Howard [MVP]

FMCyb --

Your Project Server administrator should do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. In the Time Period Settings section, enter 24 in the Maximum number of
hours... field
4. Click the Save Changes button

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top