Restructure Resource IDs in a project

  • Thread starter projectserverdragon
  • Start date
P

projectserverdragon

I once saw an article on how we could change the resourceID of the resource
sheet and now I can't find it.

Anyone recall this?

thx in adv. PSD
 
R

Rod Gill

Hi,

You can sort with renumber option set (Project, Sort). In Project Server
your Resource GUID will remain unchanged, but the ID will change.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
P

projectserverdragon

I did this and the sort saved; however it did not restructure my ID's.

Have you executed this in MSPS 2003 SP3?
 
R

Rod Gill

OK, you had better explain what you mean by restructure as Resource IDs are
numerical and in sequence, no change possible other than through sorting.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
J

Jonathan Sofer [MVP]

Are you trying to use the sorting feature "Permanently renumber resources"?
This option does not work in Project Server 2003 like it would on a
standalone mpp file with local resources. Meaning that it will not retain
the new resource IDs when saving schedules on the server.

Sorry for the bad news,
Jonathan
 