A
Anonymous
Hi,
I want to retrieve the SPI of a previous status date using VBA/macro in MSP
2003 server.
e.g.
I have rebaselined my schedule this week. I believe if I just change status
date and take the SPI of the summary task it will not give me the correct SPI
as it was before rebaselining. Is there anyway to get the true SPI
programmatically.
Thanks for help!
I want to retrieve the SPI of a previous status date using VBA/macro in MSP
2003 server.
e.g.
I have rebaselined my schedule this week. I believe if I just change status
date and take the SPI of the summary task it will not give me the correct SPI
as it was before rebaselining. Is there anyway to get the true SPI
programmatically.
Thanks for help!