Revising a schedule for a project that was put on hold

S

Sam

I had a complete schedule for a project that was fully underway, and then was put on hold for 3 months. Many of the tasks are partially or 100% complete. The project has now been restarted, and I am trying to bring the schedule up to date.

When I look at the schedule, all of the tasks are still showing dates in the past, even the ones that are 0% complete. Is there an easy way to bring them to the current dates? I.e., if a task hasn't been started, it doesn't make sense for it to have a start/finish date in the past. I don't want to "force" dates using "Start no later than" constraints... I would like for Project to calcuate the ones that need to have their dates moved to the present.
 
J

JackD

Go to tools menu / tracking / update project and set the uncompleted work to
start after the date of your choice.
I'm afraid it will split tasks and use a delay in order to achieve this but
there is no way around that.

-Jack


Sam said:
I had a complete schedule for a project that was fully underway, and then
was put on hold for 3 months. Many of the tasks are partially or 100%
complete. The project has now been restarted, and I am trying to bring the
schedule up to date.
When I look at the schedule, all of the tasks are still showing dates in
the past, even the ones that are 0% complete. Is there an easy way to bring
them to the current dates? I.e., if a task hasn't been started, it doesn't
make sense for it to have a start/finish date in the past. I don't want to
"force" dates using "Start no later than" constraints... I would like for
Project to calcuate the ones that need to have their dates moved to the
present.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top