Risks & Issues

R

RandyK

Is there a way that we can report on risks and issues accross the enterprise
(all projects) in MSPS (2003)?

For example, we have 250 active projects and we want to report on all high
prioirty issues accross all projects - or perhaps a report that lists all
risks accross all projects with probability of occurence greater than 60%.
Are these types of reports possible in MSPS? If so, how? (or do we need to
mine the data using a third party system?)
 
D

Dale Howard [MVP]

RandyK --

You need to use a reporting tool such as Crystal Reports or SQL Reporting
Services. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top