Rick:
It's all about the assignment data. 423 assignments against 80 tasks is
substantial. If you haven't done the rebuild, I'd try this first:
http://www.projectserverexperts.com/Shared Documents/BinaryRebuild.htm
If you have done the rebuild by saving as XML, you should also run the
routine in the link above. The XML save bloats the file considerably and
this will shrink it back to normal size.
Hi,
Thanks, I think we will have to go ahead with re-building the plan just
to
get the PM back up and running with a working plan. The installation is
medium sized with about 100 plans, about 20 large (500 task) plans all
on
one
large server (4 x 3ghz Xeon hyperthreaded processors, 16gb RAM) ....
but I
think this also restricts us to a single view notify process which is
why
this is an issue.
Regards
Richard
:
Richard,
If you don't want to waste too much time you might want to go ahead
and
perform the steps I have recommended in the last post. This is a
quick-and-dirty approach that will solve the problem for the moment;
however
it can always occur again.
Are we talking about a large installation of Project Server in your
case?
Marc S.
MCP for EPM
www.diventis.ch
msepm.blogspot.com
Hi,
Thanks for the response and I was reluctantly coming to the same
conclusion.
We are on SP2a.
Regards
Richard
:
Richard,
One of our customer was experiencing similar issues with some
project
plans.
The only way to solve this turned out to be an export of the plan
to
XML
to
then re-import it (using the wizard) and save it as a new plan.
Which version of Project Server 2003 are you running? SP1 or SP2?
There
were
a couple of issues with Views Notification Service addressed with
SP2.
Marc S.
MCP for EPM
www.diventis.ch
msepm.blogspot.com
Hi,
Thanks for the reply. We have tried restarting the VN process,
but
that
makes no difference. I have also done timings with other project
plans
and
plans with many more tasks and assignments and they are taking
20 -
30
minutes to process ..... which looking through the Microsoft
Configuration
Planning Guide still seems on the long side, but much less than
this
particular plan.
Regards
Richard
:
Richard,
Do you have other similar plans that cause the same problem?
Have you tried deleting the XML file from the ViewDrop folder
and
then
restarting the Views Notification Service?
Let us know...
Marc S.
MCP for EPM
www.diventis.ch
msepm.blogspot.com
Hi,
We have a plan which is taking several hours for the View
Notify
process
???
We are running PS SP2a and a single viewnotify process, so
this
is
causing
a
blockage. The server hardware is not stressed (single server
with
4
x
Xeon
hyperthreaded processors rarely over 50%, 16gb RAM and disk
usage
is
low)
We
are also running managed time periods ... any ideas?
I have removed [ ] and & characters from the task names (but
left
the .
, -
and ( )) and also changed the registry setting to raise the VN
process
priority to 6, but no improvement????
Some project plan details .....
Tasks - 80
Assignments - 423
Resources - 97
... so not a big plan.
Many thanks
Richard