M
Michael Balda
I am importing a project. When it imports tasks and all parts of the
project, it shows completed tasks starting on the project date - which mucks
up everything. How do I make all completed tasks and partial completed tasks
show on the Gantt chart-start-end dates as complete before the start date of
the project? For example a 5 day task is complete, then another task is
linked to it which is 5 days - Project is showing the uncompleted 5 day task
can not start for 10 days because the completed task that is 100% complete
can not start until the start date of the project. I have similar issue with
partial completed tasks. Appreciate your help on changing a setting
somewhere.. Is this clear to you? If not let me know. Again, Project starts
9-30-05, I import a completed task which duration is 5 days project shows the
completed tasks starts today’s date 10-05-05 ends 10-10-05, the next
uncompleted task linked to this one starts 10-11-05 and ends 10-16-05 -- The
uncompleted task should be able to start as of today’s date.. --- I need to
roll back, get completed tasks to show complete before today’s date...
project, it shows completed tasks starting on the project date - which mucks
up everything. How do I make all completed tasks and partial completed tasks
show on the Gantt chart-start-end dates as complete before the start date of
the project? For example a 5 day task is complete, then another task is
linked to it which is 5 days - Project is showing the uncompleted 5 day task
can not start for 10 days because the completed task that is 100% complete
can not start until the start date of the project. I have similar issue with
partial completed tasks. Appreciate your help on changing a setting
somewhere.. Is this clear to you? If not let me know. Again, Project starts
9-30-05, I import a completed task which duration is 5 days project shows the
completed tasks starts today’s date 10-05-05 ends 10-10-05, the next
uncompleted task linked to this one starts 10-11-05 and ends 10-16-05 -- The
uncompleted task should be able to start as of today’s date.. --- I need to
roll back, get completed tasks to show complete before today’s date...