Roll up baseline

T

Thomas

I have insertet four subprojects into a master project. I open every one of them from the masterproject (outline level) and values in the row representing the inserted subproject are updated accordingly - except for "Baseline Work". This value is rolled up to the top level in each subproject, but it is not rolled up/reflected in the line representing the subproject in the masterproject. Why?
 
G

Gérard Ducouret

Thomas,
The master project is a different file by its own. So you have to record its
own baseline :
Tools/ Tracking / Save baseline

Gérard Ducouret

Thomas said:
I have insertet four subprojects into a master project. I open every one
of them from the masterproject (outline level) and values in the row
representing the inserted subproject are updated accordingly - except for
"Baseline Work". This value is rolled up to the top level in each
subproject, but it is not rolled up/reflected in the line representing the
subproject in the masterproject. Why?
 