A
Ali
Hi,
I was wondering if anyone knew how to create the following view (using out
of the box functionality, or macros, or even with plugins):
March 1 2 3 4 5 6 7 8 9 10 11
Person1 [--task1--][task2][----task3----]
Person2 [task4][-----------task5----------]
....
Basically, i want to be able to see what each person is going to be working
on for a period of time, with all of their tasks on the same line. there are
two views that are somewhat close:
a) the task rollup view gantt chart which rolls up subtasks by higher level
task.
b) the resource usage view that shows the number of hours worked by each
resource, but doesn't put the task names on one line.
I would think this would be very useful to everyone using Project, but i
can't seem to find a way to do it.
Please HELP!
thanks,
-=> Ali
I was wondering if anyone knew how to create the following view (using out
of the box functionality, or macros, or even with plugins):
March 1 2 3 4 5 6 7 8 9 10 11
Person1 [--task1--][task2][----task3----]
Person2 [task4][-----------task5----------]
....
Basically, i want to be able to see what each person is going to be working
on for a period of time, with all of their tasks on the same line. there are
two views that are somewhat close:
a) the task rollup view gantt chart which rolls up subtasks by higher level
task.
b) the resource usage view that shows the number of hours worked by each
resource, but doesn't put the task names on one line.
I would think this would be very useful to everyone using Project, but i
can't seem to find a way to do it.
Please HELP!
thanks,
-=> Ali