T
Tim
Can anyone give me a pointer for usage of MS Project 2002?
The problem is this: I have an overall task, "Overall 1",
to which I don't associate any duration. It is present
just to keep things organized logically. I assign that
task to "Resource A", just for ownership. Once again,
there is no explicit work for "Resource A" to perform.
Underneath "Overall 1", I have "Subtask 1" and "Subtask
2", which do have durations associated with them. Also, I
assign one of them to "Resource A" and "Resource B". When
I go to look at the Resource Usage View to see if my
resources are overbooked, it looks like "Resource A" is
overbooked, because it treats "Overall 1" as a real task
that needs to be performed. That is not what I meant by
assigning ownership of it to "Resource A". There must be
an easy way to tell Project to not treat this as a task,
but I haven't found it yet. Any thoughts?
The problem is this: I have an overall task, "Overall 1",
to which I don't associate any duration. It is present
just to keep things organized logically. I assign that
task to "Resource A", just for ownership. Once again,
there is no explicit work for "Resource A" to perform.
Underneath "Overall 1", I have "Subtask 1" and "Subtask
2", which do have durations associated with them. Also, I
assign one of them to "Resource A" and "Resource B". When
I go to look at the Resource Usage View to see if my
resources are overbooked, it looks like "Resource A" is
overbooked, because it treats "Overall 1" as a real task
that needs to be performed. That is not what I meant by
assigning ownership of it to "Resource A". There must be
an easy way to tell Project to not treat this as a task,
but I haven't found it yet. Any thoughts?