Roll-up totals in Resource Usage view Project 2000

T

TroyK

G'day,

In Project 2002, when I look at the Resource Usage view and do a roll-up
(sorted by groups) I see totals at the roll-up level (for each group).
However, when a co-worker looks at the same view in Project 2000 they don't
see the totals at the roll-up level, only below. So they have to copy and
past into Excel to do totals. Is there anyway to do this in 2000, or is it a
feature only available in 2002?

Many thanks,

Troy
 
R

Rod Gill

Hi,

They ran out of time to do roll up totals in P2000. This was finished in
P2002.

--
Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top