D
Dave
I have a Prj03 file with about 500 tasks in a dozen projects. Most of
the summaries display progress consistently (ActualStart - Complete
Through), but there are a couple that persistently display 99%
complete when only the first one or two subtasks are 100% complete.
For these summaries it is also impossible to set % complete manually -
manual changes revert to 99% (% complete can be set manually to any
value for the other summaries). Does anybody have any suggestions?
Thanks
Dave
the summaries display progress consistently (ActualStart - Complete
Through), but there are a couple that persistently display 99%
complete when only the first one or two subtasks are 100% complete.
For these summaries it is also impossible to set % complete manually -
manual changes revert to 99% (% complete can be set manually to any
value for the other summaries). Does anybody have any suggestions?
Thanks
Dave