Rolling up BCWS in task usage view

B

Brendan F

I discovered that a task in my Project plan was showing a BCWS of $0 when
there should have been a value. The status date was set later than the
baseline finish of the task to make sure that all of the work for that task
would be captured in the BCWS.
When I went to the task usage view, I noticed that each resource had a
correct BCWS value, but this value was not rolling up to the task line.
Because it was not rolling up, the BCWS for the task was showing $0.
Does anybody know what may be causing this?
Thank you.
 