M
MT
How does MS Project roll up total slack and critical columns of tasks to the
summary task level?
I had intuitively assumed that it was based on the final task of te summary
task, but I have a summary task with 3 sub-tasks. The first 2 are critical,
and the 3rd is not, and the summary task is showing critical.
I would like to know this, because I would like a way to report on
critical-path health at the summary task level without having to delve into
the sub-task details.
summary task level?
I had intuitively assumed that it was based on the final task of te summary
task, but I have a summary task with 3 sub-tasks. The first 2 are critical,
and the 3rd is not, and the summary task is showing critical.
I would like to know this, because I would like a way to report on
critical-path health at the summary task level without having to delve into
the sub-task details.