Hi, I have put together a relatively straightforward project plan, which has
4 outline levels. At level 4 all of the dates are milestones.
How can i roll up the milestones to appear on the gantt bars at outline
level 3, and not roll up any further (to levels 2 and 1) - it makes my plan
look really messy and somewhat incomprehensible!
Any help would be really appreciated.
Ashley