My Boss Needs me to provide him with rolled up %age usage for resources
The Issue is that In Task Usage View Resources are only allocated at task
level - they are not rolled up
in the same way that work is rolled up in the gantt
is there any way to do this ?
My Plans typically consist of
So If I Had 1 resource (R1) and he was 10% on Task 1a1, 20% hrs on Task 1b1
and 60% hrs on tasks 2a1
And we assumed concurrent tasks
His Hours would be
1 At Program Level: 90% utilisation
2. At Project1 Level: 30% utilisation
3 at Project 2 Level 60% utilisation
clearly over a tamespan these percentages would vary as tasks started and
finished..
Please can someone throw some light on this for me
I'm using MSP 2003
The Issue is that In Task Usage View Resources are only allocated at task
level - they are not rolled up
in the same way that work is rolled up in the gantt
is there any way to do this ?
My Plans typically consist of
Programme Level
So If I Had 1 resource (R1) and he was 10% on Task 1a1, 20% hrs on Task 1b1
and 60% hrs on tasks 2a1
And we assumed concurrent tasks
His Hours would be
1 At Program Level: 90% utilisation
2. At Project1 Level: 30% utilisation
3 at Project 2 Level 60% utilisation
clearly over a tamespan these percentages would vary as tasks started and
finished..
Please can someone throw some light on this for me
I'm using MSP 2003