Rollup a Custome enterprise field (cost task field) to cost projectfiled

V

Vit

Hi all,

I have created a custom task cost field that works fine, but I was
wondering if it is possible to have the "project value" in in a
project cost field...

in the gantt view I can see the total, but I need to see the same
total in the project centre view...

thanks for your suggestions

cheers

Vit
 
B

Ben

Hi Vit, set the roll-up field to SUM within the task custom field. Create a
new Project Level cost field, and make it equal to the name of the task level
field. Eg if the task level field is called task_value, then the project
level field is equal to [task_value]
 