D
Dave
Based on certain criteria, we identify a specific milestone as THE
project milestone (we call it the "Go-Live Milestone") and mark it with
a flag. I want to display the name of that task/milestone in a PWA
view to look something like this:
Project Name Go-Live Milestone Name Go-Live Date
Test Project Test Sys Complete 6/7/2006
Obviously, no problem with the Project Name or the Date field (I can
get the flagged task's date to rollup to the project summary task level
so I can "transfer" it to an Enterprise Project field to display in
PWA). What I can't do is figure out how to "rollup" the "Go-Live
Milestone Name" (a text field) to the project summary task so I can
pick it up in a Enterprise Project Text field to display in PWA. I
must be missing something obvious, but how can I do this?
Thanks
project milestone (we call it the "Go-Live Milestone") and mark it with
a flag. I want to display the name of that task/milestone in a PWA
view to look something like this:
Project Name Go-Live Milestone Name Go-Live Date
Test Project Test Sys Complete 6/7/2006
Obviously, no problem with the Project Name or the Date field (I can
get the flagged task's date to rollup to the project summary task level
so I can "transfer" it to an Enterprise Project field to display in
PWA). What I can't do is figure out how to "rollup" the "Go-Live
Milestone Name" (a text field) to the project summary task so I can
pick it up in a Enterprise Project Text field to display in PWA. I
must be missing something obvious, but how can I do this?
Thanks