J
JB
I am looking at a project plan created by an employee and I am not sure how
to answer this issue. We are using Project Server 2003. However, he is not
using PWA to have the percent work complete updated by his resources.
Instead he is entering them in by hand in the project plan itself. The
problem is that some, not all, of the rollup (summary level) tasks are
showing 99% complete with all of the subordinate level tasks underneath
showing 100% complete. Why is the rollup not showing 100%? Also, he has
resource names attached to the summary level tasks that showing 99%, not 100%
complete. Why is this happening? I noticed that when I delete the summary
level resource, the percent complete changes to 100% like it should. I know
that you are not supposed to have resources for summary level tasks and they
will be changed. However, agian, why is this happening?
to answer this issue. We are using Project Server 2003. However, he is not
using PWA to have the percent work complete updated by his resources.
Instead he is entering them in by hand in the project plan itself. The
problem is that some, not all, of the rollup (summary level) tasks are
showing 99% complete with all of the subordinate level tasks underneath
showing 100% complete. Why is the rollup not showing 100%? Also, he has
resource names attached to the summary level tasks that showing 99%, not 100%
complete. Why is this happening? I noticed that when I delete the summary
level resource, the percent complete changes to 100% like it should. I know
that you are not supposed to have resources for summary level tasks and they
will be changed. However, agian, why is this happening?