Marc Soester
Hi,
Instead of having the “finish†description for the finish column within PWA
Project center, we would like to rename it “forecast finishâ€. I have
configured an Enterprise custom field type â€date†and have given it the name
“Forecast Finish†with the formula [finish].
I have changed my PWA view to include this custom field – So far so good.
Unfortunately when I now check my view, the custom field does not roll up
the value within my outline codes ( program and portfolio outline code). I
did change the “Calculation for task and group summary rows†to maximum when
I created my custom field, but no luck.
In order for me to check my finish date for my program, I will need to have
this roll up functionality within my Project Center, preferably with the
naming convention “forecast finishâ€.
Any ideas how to achieve this.
Many thanks
Marc
Instead of having the “finish†description for the finish column within PWA
Project center, we would like to rename it “forecast finishâ€. I have
configured an Enterprise custom field type â€date†and have given it the name
“Forecast Finish†with the formula [finish].
I have changed my PWA view to include this custom field – So far so good.
Unfortunately when I now check my view, the custom field does not roll up
the value within my outline codes ( program and portfolio outline code). I
did change the “Calculation for task and group summary rows†to maximum when
I created my custom field, but no luck.
In order for me to check my finish date for my program, I will need to have
this roll up functionality within my Project Center, preferably with the
naming convention “forecast finishâ€.
Any ideas how to achieve this.
Many thanks
Marc