peter
Hi,
Does anyone know how to stop the following occuring in
Microsoft Project (98);
When I enter a new task of 1 day and a start date of
23/03/04 then project defaults an end date of 24/03/04,
which to me indicates a 2 day task.
If I change the finish date to 23/03/04 the project then
changes the duration from 1 day to 0.88 days.
Thanks in advance.