D
dnshanno
I'm encountering a rounding error problem when entering
tasks on my ms-project's. For some reason, it takes .02
of an hour, for example instead of putting my actuals at
50.5 hours ms-project makes it 50.48 - even though 50.5
was entered. Why is this happening? Is there a work
around?
tasks on my ms-project's. For some reason, it takes .02
of an hour, for example instead of putting my actuals at
50.5 hours ms-project makes it 50.48 - even though 50.5
was entered. Why is this happening? Is there a work
around?