Row Numbering

A

Aarti

Hi All

As I am creating my project plan, with a whole bunch of tasks under it - i realise that the row number is incorrect for example row 186 and then suddenly row 218

I have as my settings no filters and I have a number of times clicked on show sub tasks but to no end

If I expand and collapse the tasks sometimes missing rows appear and sometimes they still don't !

Whacky or what?

If there are any explanations/solutions I'd llike to hear about i

Thanks
 
A

Andrew Kazarinoff

Do you have a repeating task after 186?

----- Aarti wrote: ----

Hi All

As I am creating my project plan, with a whole bunch of tasks under it - i realise that the row number is incorrect for example row 186 and then suddenly row 218

I have as my settings no filters and I have a number of times clicked on show sub tasks but to no end

If I expand and collapse the tasks sometimes missing rows appear and sometimes they still don't !

Whacky or what?

If there are any explanations/solutions I'd llike to hear about i

Thanks
 
J

John

Aarti,
Three other suggestions beyond what Andrew offered. First, check to see
if the tasks are sorted by something other than task ID. Second, if the
file is a master file with inserted subprojects, try opening the
subprojects and then use the "Show subtasks". Third, if the file has
external links to another file, check the setting of Tools/Options/View
tab and ensure that the two check boxes for external predecessors and
successors is checked.

Hope this helps.
John
 