S-curve exported to excel

L

labingtone

Hi,
There are some threads here that talks about the generating S-Curve. I did
follow the procedure but I am not getting a curve. all points were zeros.
I want to see the curve between the the Plan progress and the actual
progress of the work in terms of time. What is the proper way to do this.
 
J

Jim Aksel

You need costed resources assigned to tasks and a baseline. You also need a
%Complete for the tasks. A properly statused schedule is required to obtain
good data.

There is a quirk if you want to generate data past the status date because
MS Project will not give you data to the right of the status date. To solve
the problem set the status date past the last day of your project. Now
export to Excel.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 