Johan said:
How do I draw a S-Curve from the info on my Project Schedule?
Johan,
You will first need to export the timescaled data to Excel (or other
graphing application). To do that you can use various methods. One is to
use the "Analyze timescaled data in Excel" utility/add-in found on the
Analysis toolbar. Another is to create your own VBA macro that gathers,
exports, and graphs the data. A third is to go to our MVP website at:
http://project.mvps.org/vbacode.htm
and look for fellow MVP, Rod Gill's link to his website
(
www.msproject-systems.com)
Rod has various analysis macros including one that generates S-curves.
Hope this helps.
John
Project MVP