J
James Ferrise
We want to capture resources' Actual Hours on their
projects. However, in providing cost and budget
information, we want to limit the calculation of such to
be the resources' rate * a maximum of 40 hours per week.
This is because many of the resources are salaried exempt
employees. So, even though we want to capture the Actual
Hours they worked, we do not want to calculate the impact
to the total project cost beyond the limits of their
salary. What are our options in this situation?
projects. However, in providing cost and budget
information, we want to limit the calculation of such to
be the resources' rate * a maximum of 40 hours per week.
This is because many of the resources are salaried exempt
employees. So, even though we want to capture the Actual
Hours they worked, we do not want to calculate the impact
to the total project cost beyond the limits of their
salary. What are our options in this situation?