Hi all,
I have a consolidated Master file which contains approx 15
inserted projects.
A project leader updates one of the projects, which in
turn shows in the consolidated Master, BUT using other
machines, the same consolidated master shows different
work hours. Dates/duration are all the same.
How can the same Master, linked to the same inserted
project show different work values??? I have checked
pathways, tried deleting the inserted project and
inserting again. Nothing seems to help.
Has anyone else experienced this, and if so what was the
problem in "your" case???
Thanks
Robert
I have a consolidated Master file which contains approx 15
inserted projects.
A project leader updates one of the projects, which in
turn shows in the consolidated Master, BUT using other
machines, the same consolidated master shows different
work hours. Dates/duration are all the same.
How can the same Master, linked to the same inserted
project show different work values??? I have checked
pathways, tried deleting the inserted project and
inserting again. Nothing seems to help.
Has anyone else experienced this, and if so what was the
problem in "your" case???
Thanks
Robert