Hi,
I have a resource that was importing her time by clicking on import
timesheet, highlighting the correct week, clicking on import, clicking on the
checkbox to select all of her tasks and then clicking on submit selected.
However, her time wouldn't import into the project plan. Instead, she clicked
on save all before clicking on submit selected and all of her time came
through. What is the difference between clicking on save all and submit
selected? How does that save all work?
Thanks,
I have a resource that was importing her time by clicking on import
timesheet, highlighting the correct week, clicking on import, clicking on the
checkbox to select all of her tasks and then clicking on submit selected.
However, her time wouldn't import into the project plan. Instead, she clicked
on save all before clicking on submit selected and all of her time came
through. What is the difference between clicking on save all and submit
selected? How does that save all work?