Hello,

We have Project Server 2003.
I want to save baseline (Baseline 0) once a week, at the same day for all
Gantts (30-40 gantts).

Is it possible to do it automatically ?

Thanks

Perl
 
G

Gary L. Chefetz [MVP]

Perl:

It's difficult to imagine why you would rebaseline a project on a weekly
basis. Accepting that you have good reason, you could write a macro to do
this, and possilby setup a schedule job. Depending on how automated you want
it, determines how much coding you have to do. See the following for some
ideas how to proceed. You 'll need to adapt these instructions for your use:

http://www.projectserverexperts.com/Shared Documents/ApplyFormulaToAllProjects.htm

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
 
R

Rod Gill

Saving to baseline saves baseline data for all Views. For time critical
projects I often advocate saving to Baseline every week just before
timesheet updates. That way you can see the weekly trend for progress.
However project 2007 updates do show you this but only when actually
updating and the view is not available once the update is complete.

I save to Baseline1 after phase1 is scheduled, Baseline 2 after phase 2 is
scheduled and so on. I also create Tracking Gantt1,1 etc so it's easy to see
current progress against any baseline.

--

Rod Gill
Project MVP

Project VBA Book, for details visit:
http://www.projectvbabook.com

NEW!! Web based VBA training course delivered by me. For details visit:
http://projectservertraining.com/learning/index.aspx
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top