Keep in mind the Master Project is a separate project with its own baseline.
When saving a baselines for the Master Project, you save baseline
information for those activities that are not subprojects. For example, you
may have program level information and tasks that cover all the
subprojects.... things like "Project Management", "Undistributed Budget",
"Risk Activities", etc.
Subproject baselines are for the individual subprojects themselves. For
example, you would maintain a separate baseline for phases of a project, or
departments such as Systems Engineering. Perfectly reasonable to keep these
baselines separate -- that is probably the "normal" way to do business.
Saving a MP Baseline does not propagate down to the inserted projects (which
have their own baselines.). It just so happens I was working a project
recently where it would be convenient to save baslines to all projects
(master/sub) and to do this weekly (never mind, long story)... I have a Macro
in a Module that will recursively push a baseline save (in my case Baseline5)
down to the master/sub projects. Post back if you would like me to put it up
for you.
--
If this post was helpful, please consider rating it.
Jim
It's software; it's not allowed to win.
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project