greghoro
I'm trying to figure out the logic behind the "Save interim planâ€
functionality.
What I have observed. When I use this to copy Baseline into Baseline1, is
that it does a one for one copy of all Baseline data (work, dates, cost,
duration) into its corresponding Baseline1 field for each task in the Table
area of a usage view.
However, the Timescaled data that is copied into Baseline1 Work is the
current value for Work and not Baseline Work as I would have expected. This
results in a situation where the Timescaled side may not add up to the Table
side for a task.
Is there a logical explanation for this behavior?
Greg
Is there a locgical explanation for this behavior?
Greg
functionality.
What I have observed. When I use this to copy Baseline into Baseline1, is
that it does a one for one copy of all Baseline data (work, dates, cost,
duration) into its corresponding Baseline1 field for each task in the Table
area of a usage view.
However, the Timescaled data that is copied into Baseline1 Work is the
current value for Work and not Baseline Work as I would have expected. This
results in a situation where the Timescaled side may not add up to the Table
side for a task.
Is there a logical explanation for this behavior?
Greg
Is there a locgical explanation for this behavior?
Greg