save start date to compair with actual start date.

L

lhankg

As I input actual start dates the start date also changes. Can I track the
original start date vs actual start date in any report? I would like to
compair the 2 dates in weekly meetings.
 
J

JulieD

Hi

prior to entering the actual information, baseline your project (tools /
tracking / save baseline), this will give you the ability to compare actual
to planned. You can also use the tracking gantt view to see both the
baseline & actual (current) on the same gantt chart.

Cheers
JulieD
 