C
crosby.tim
We are using Project Standard 2002. We have a project file that one PM
is creating and he needs to make the current week's tasks visible to
about 15 other people. We figured out how to create a filter that will
only show this week's tasks. The problem is that when you close the
project file and reopen it, it defaults back to the "All Tasks" filter.
Is there a way to save the project so that it always open with that
filter applied?
The problem is that the 15 people who need to view this project don't
have MS Project licenses so we got them a 3rd party product called
"Projette". This allows them to view project files. Unfortunately, it
does not allow those users to select a filter for the project plan.
is creating and he needs to make the current week's tasks visible to
about 15 other people. We figured out how to create a filter that will
only show this week's tasks. The problem is that when you close the
project file and reopen it, it defaults back to the "All Tasks" filter.
Is there a way to save the project so that it always open with that
filter applied?
The problem is that the 15 people who need to view this project don't
have MS Project licenses so we got them a 3rd party product called
"Projette". This allows them to view project files. Unfortunately, it
does not allow those users to select a filter for the project plan.