Hello Steve,
You can save the data from the reporting database through Report >
Visual Reports. In the create Report dialog click the "Save data"
button and in the Save reporting data dialog, click the Save
database button.
Note, this is only the data from the reporting db. See the Project
2007 SDK for information on working with the reporting db.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project