If I have a regular gantt table view with multiple levels of indents, is
there any way to save a customized view of select levels being shown? In
other words, I might want only some level 2 tasks under certain summary
activiteis, and then mabye leve 2 & 3 under others. Basically, what I'm
looking for is something like a save current view

Larry
 
J

Jim Spiller

Whether subtasks are expanded or collapsed is not something that can be
saved with a view. Expanding and collapsing tasks is program wide. You can
save your file with certain levels shown but if you expand/collapse summary
tasks this will affect all (task) views.
 
L

larry

would really help and make a great enhancement, oh well, need to figure out a
logical filtering system I guess
 