I saved the project plan as an interim plan before baselining it. I hav
two new columns Start1 & Finish1 to track the new progress.However. Th
Finish 1 is not getting updated automatically when I put the date i
Start1. I inserted an precedessor column but it still does no
automaticaly update the Finish1
can someone please help on how to get this working . So that I have th
planned start & finish ( my orginal dates), start1 & finish 1 (interi
dates)
Thanks a ton