Saving Baseline for Proejct Paln

N

NewsGroup

I have created a proejct plan,saved a baseline and published it.
I wanted to overwrite the baseline already saved.
I have done that in the published version of the project and republished the
assignemnts.
But I am not able to see the changes in PWA.
How do I make sure that it changes in PWA also?

Meena
 
D

Dale Howard [MVP]

Meena --

After you resave the baseline, you should also click Collaborate - Publish -
All Information. Hope this helps.
 