M
Micha P
I'm trying to set baseline to 3 sub-projects in a consolidated file on
project 2007 pro stand-alone.
1.Expanded all tasks
2.Selected all tasks
3.tools->tracking-set baseline
4.checked the "selected tasks" radio button
5.clicked OK
And the project crashed.
Am I doing something wrong?
Is there a best practice on saving baselines on a master project?
M
project 2007 pro stand-alone.
1.Expanded all tasks
2.Selected all tasks
3.tools->tracking-set baseline
4.checked the "selected tasks" radio button
5.clicked OK
And the project crashed.
Am I doing something wrong?
Is there a best practice on saving baselines on a master project?