O
oid
Hello
Being relatively new to Project Pro and Project Server I am having a
problem on what seems to be somethign quite basic.
I set up 2 projects in Project Pro and in each one there is a single
task of 3 days duration starting and finishing on the same day. Each
task is allocated to the same enterprise resource and when I allocate
it to the second task the task is shunted along the gantt chart so that
the resource is not over-allocated.
When I save or publish the projects the tasks revert back to occuring
at the same time and the resource being overallocated. This is
displayed in the resource sheet view. I can level the resources again
but when i try to save and/or publish it reverts back to being
over-allocated.
Is there some setting on Project Server that I have not set correctly?
Cheers
Being relatively new to Project Pro and Project Server I am having a
problem on what seems to be somethign quite basic.
I set up 2 projects in Project Pro and in each one there is a single
task of 3 days duration starting and finishing on the same day. Each
task is allocated to the same enterprise resource and when I allocate
it to the second task the task is shunted along the gantt chart so that
the resource is not over-allocated.
When I save or publish the projects the tasks revert back to occuring
at the same time and the resource being overallocated. This is
displayed in the resource sheet view. I can level the resources again
but when i try to save and/or publish it reverts back to being
over-allocated.
Is there some setting on Project Server that I have not set correctly?
Cheers