Hello
I am very new to Project so I am probably making some basic mistake
however this is my problem:
I have 2 very basic Projects PROJ1 and PROJ2 using the same enterprise
resources R1 and R2. I can level the resources fine so that the days
allocated to tasks for each resource don't clash. However when I try to
save the projects at this point the levelling reverts back and the
resources are overallocated.
Can anyone help?
Cheers
I am very new to Project so I am probably making some basic mistake
however this is my problem:
I have 2 very basic Projects PROJ1 and PROJ2 using the same enterprise
resources R1 and R2. I can level the resources fine so that the days
allocated to tasks for each resource don't clash. However when I try to
save the projects at this point the levelling reverts back and the
resources are overallocated.
Can anyone help?