R
RandySeattle
I am maintaining a Master Schedule with 12 individual projects in
Project 2003 Standard, with quite a few external linkages between them
(all told, the file is about 2500 tasks). All of the files are
maintained in a single file and there are no linkages to files outside
of the folder. All of the files are maintained by one person (me).
My question is this: How can I run scenarios on the individual
schedules to run comparison reports without creating a bunch of
"phantom" external linkages (I know that it's not possible to run
comparisons on inserted projects). Prior to the Master Schedule, I
would have simply done a "save as" with a new name, made the
anticipated changes to the new file and run a comparison report. But
now that we are maintaing a Master Schedule with external linkages
between the projects, if I copy or save as new external links are
created in the Master File.
I have tried a couple of different ways of doing this and the result is
the same. I have to go into the newly created file, and delete all of
the external links. But because some of these projects are also master
projects in their own right (There are 5 projects that make up the
"master", but 12 projects in total because some of the 5 have
sub-projects of their own) this is a time consuming and often
frustrating process, that is fraught with danger of corruption. I have
already had to rebuild the master file once from scratch because of
some bad links.
Does anyone know of a good way to be able to do this? Management often
wants to play what-if games with the schedule to see what the impacts
of changes to the schedule would be. There should be an easier way of
doing this.
Any thoughts would be appreciated.
Randy
Project 2003 Standard, with quite a few external linkages between them
(all told, the file is about 2500 tasks). All of the files are
maintained in a single file and there are no linkages to files outside
of the folder. All of the files are maintained by one person (me).
My question is this: How can I run scenarios on the individual
schedules to run comparison reports without creating a bunch of
"phantom" external linkages (I know that it's not possible to run
comparisons on inserted projects). Prior to the Master Schedule, I
would have simply done a "save as" with a new name, made the
anticipated changes to the new file and run a comparison report. But
now that we are maintaing a Master Schedule with external linkages
between the projects, if I copy or save as new external links are
created in the Master File.
I have tried a couple of different ways of doing this and the result is
the same. I have to go into the newly created file, and delete all of
the external links. But because some of these projects are also master
projects in their own right (There are 5 projects that make up the
"master", but 12 projects in total because some of the 5 have
sub-projects of their own) this is a time consuming and often
frustrating process, that is fraught with danger of corruption. I have
already had to rebuild the master file once from scratch because of
some bad links.
Does anyone know of a good way to be able to do this? Management often
wants to play what-if games with the schedule to see what the impacts
of changes to the schedule would be. There should be an easier way of
doing this.
Any thoughts would be appreciated.
Randy