What are the steps to follow while schule revising.. i want to revise
the schedule as schedules. not as per progress at site.... please
advise me .....

I mean, already saved Baseline 01, want to change the dates as
schedules previously.....i am confusing .....
 
J

Jan De Messemaeker

Hi,

First, I would set Baseline, not Baseline1: it is handled more completely.
Then you can change your schedule as needed.
You can compare the revised schedule dates to the baseline two ways:

1. Show the Tracking Gantt view (View Menu)
2. Use the Variance Table (View menu, Table:... , Click Variance) which
shows the deviatios vis à vis baseline.

Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top