P
pyper72
I'm trying to schedule a deliverable that is due 15 calendar days after the
award date. Is there any way I can use a predecessor task that is the
contract award with a lag to schedule this? When I use a normal lag it uses
working days. I don't think I'll be able to change the calendar as it will
be going into project server where the calendar is fixed.
award date. Is there any way I can use a predecessor task that is the
contract award with a lag to schedule this? When I use a normal lag it uses
working days. I don't think I'll be able to change the calendar as it will
be going into project server where the calendar is fixed.