Hello.
I know there is a setting that allows PMs to schedule tasks on a nonworking
day in project plan. They are prompted with the option to "Make this
nonworking day a working day?". I do not want to change the enterprise
calendar, I would like the PMs to have the option on a task-by-task,
project-specific basis. I am unable to find this setting in PWA admin or any
of the documentation. Help, please!
Thank you,
Louise Anderson