J
John Garay - DecisionEdge
I would appreciate some help understanding the way MSP works as I transition
from Primavera:
Why are unfinished tasks not moved to the right of the project status date?
There's no way a task can happen to the left - so why doesn't MSP push an
unstarted task forward to the project status date?
Here's the scenario:
Project Current Date is today: 15 Nov 07
Project Status Date is today: 15 Nov 07
Project Start Date is 2 August 2007
When I add a new task (no constraints, no predecessors), it is set to the
Project Start Date (I know this is a Schedule Option). If I force a
schedule update, the new task just sits at the project start. I would
expect it to instead move to the project status date, the soonest it can
actually happen. (I worked at Primavera for 12+ years - that's what I am
used to seeing in Primavera)
How can I get the dates of unstarted tasks to the status date?
Thanks in advance!
Regards,
John Garay
DecisionEdge, Inc.
PS - I didn't see this in the mvps FAQ
from Primavera:
Why are unfinished tasks not moved to the right of the project status date?
There's no way a task can happen to the left - so why doesn't MSP push an
unstarted task forward to the project status date?
Here's the scenario:
Project Current Date is today: 15 Nov 07
Project Status Date is today: 15 Nov 07
Project Start Date is 2 August 2007
When I add a new task (no constraints, no predecessors), it is set to the
Project Start Date (I know this is a Schedule Option). If I force a
schedule update, the new task just sits at the project start. I would
expect it to instead move to the project status date, the soonest it can
actually happen. (I worked at Primavera for 12+ years - that's what I am
used to seeing in Primavera)
How can I get the dates of unstarted tasks to the status date?
Thanks in advance!
Regards,
John Garay
DecisionEdge, Inc.
PS - I didn't see this in the mvps FAQ