schedule conflict

K

ks2008

Hi,
How do you find the schedule conflict . ? Is there any report or view
?
thanks
KS
 
D

Dale Howard [MVP]

KS --

I assume you are seeing a schedule conflict warning in the Planning Wizard
dialog. If this is not your situation, then you definitely need to
elaborate more about your problem.

Assuming you are seeing the schedule conflict warning in the Planning Wizard
dialog, then this means your schedule has slipped past an inflexible
constraint, such as a Finish No Later Than constraint. So, first, look in
the Gantt Chart view for any task that has a FNLT constraint, or any other
type of inflexible constraint, such as Must Start On (MSO) or Must Finish On
(MFO). After you locate those tasks, jot down their names and/or ID
numbers. Then, click View - Table - Schedule and pull the split bar to the
right to expose the Total Slack column. In the Total Slack column, look for
tasks that have a NEGATIVE value. You will probably see a chain of tasks
with negative slack. The last one in the chain is probably the one on which
you have the schedule conflict. To resolve the schedule conflict, you would
need to remove the constraint, or you need to replan the predecessor tasks
so that you do not slip past that constraint date. Hope this helps.
 
K

ks2008

Dale
Thanks for your input. Indeed it is great input.
I assume you are seeing a schedule conflict warning in the Plannin Wizar
dialog
Correct

Since I did notice this schedule conflict, I was curious to know, i
there any report, which can inform, the following task is havin
schedule conflict

Thank
K
 
D

Dale Howard [MVP]

KS --

No, there is no report you can run. You have to research the cause of the
problem using the steps I detailed. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top