J
Jeff Wow
I'm having a dilemma determining how to properly set up my company’s Project
schedule. The company is best classified as a custom-job manufacturing
facility. We produce jobs composed of unique-to-the-job products, in varying
quantities per job. Our contract requires us to track this fully in a
schedule, and we’ve been given Project 2003 with which to do so.
We need to track each job through a 12-step WBS. Within a job, each product
moves independently – meaning that Product A can move through Step One and
Step Two while Products B & C are still in Step One.
Currently we use each job as a summary task, with each of the 12 WBS steps
as a detail task below it. Our schedules don’t show accurate information for
each of the 12 WBS steps, but the start and end dates of the jobs themselves
are accurate enough. This is no longer accurate enough as we’ve grown in size
greatly.
My first thought was to track each product as its own summary task, with the
12 WBS steps being the detail tasks below it. But each job may have any
quantity of final products, ranging from single to triple digits, and we have
400+ jobs every year! If I did that, I’d have “12 WBS steps per product x 50+
products per job x 400+ jobs per year†number of detail tasks! As the only
scheduler, that is a bit far-fetched.
Each job will be a separate Project file, inserted into a master schedule
with a shared resource pool.
Can anyone help me out?
schedule. The company is best classified as a custom-job manufacturing
facility. We produce jobs composed of unique-to-the-job products, in varying
quantities per job. Our contract requires us to track this fully in a
schedule, and we’ve been given Project 2003 with which to do so.
We need to track each job through a 12-step WBS. Within a job, each product
moves independently – meaning that Product A can move through Step One and
Step Two while Products B & C are still in Step One.
Currently we use each job as a summary task, with each of the 12 WBS steps
as a detail task below it. Our schedules don’t show accurate information for
each of the 12 WBS steps, but the start and end dates of the jobs themselves
are accurate enough. This is no longer accurate enough as we’ve grown in size
greatly.
My first thought was to track each product as its own summary task, with the
12 WBS steps being the detail tasks below it. But each job may have any
quantity of final products, ranging from single to triple digits, and we have
400+ jobs every year! If I did that, I’d have “12 WBS steps per product x 50+
products per job x 400+ jobs per year†number of detail tasks! As the only
scheduler, that is a bit far-fetched.
Each job will be a separate Project file, inserted into a master schedule
with a shared resource pool.
Can anyone help me out?