R
Ramon de Klein
I have a problem with part-time tasks in Project. Suppose the
following situation. I have a resources "John" and "Dave" that both
work 100%.
There are two tasks that need to be done. Task #1 (75 hours) is
assigned to John and task #2 (80 hours) is assigned to Dave. Because
Dave is not very experienced it is expected that John needs to support
Dave for 12.5% of the time.
I defined the following three tasks:
1. Coaching Dave (John, fixed duration, 1 week, 12.5%)
2. Task #1 (John, fixed work, 75 hours)
3. Task #2 (Dave, fixed work, 80 hours)
I would like to have task 1 and 2 in parallel, so John spends 1 hours
per day to support Dave, which leaves 7 hours/day for task #1 the
first week. The second week John can spend 8 hours/day. Dave works 8
hours/day for two weeks on task #2. The total duration of the project
should be 2 weeks.
Unfortunately, Project doesn't understand my wish for a part-time
task. The unit for task 2 is set to 100%, so the entire task is
scheduled after task 1. If I set it to 87.5%, then the second week
John is scheduled to work 7 hours/day which is not correct.
Does anyone know how to solve this problem? I can set a task that John
has a repetitive task for 1 week for 1 hour/day, but I don't like
repetitive tasks.
I put a sample project for this scenario on my website, so please
download http://home.ict.nl/~ramklein/Photos/SampleProject.mpp
following situation. I have a resources "John" and "Dave" that both
work 100%.
There are two tasks that need to be done. Task #1 (75 hours) is
assigned to John and task #2 (80 hours) is assigned to Dave. Because
Dave is not very experienced it is expected that John needs to support
Dave for 12.5% of the time.
I defined the following three tasks:
1. Coaching Dave (John, fixed duration, 1 week, 12.5%)
2. Task #1 (John, fixed work, 75 hours)
3. Task #2 (Dave, fixed work, 80 hours)
I would like to have task 1 and 2 in parallel, so John spends 1 hours
per day to support Dave, which leaves 7 hours/day for task #1 the
first week. The second week John can spend 8 hours/day. Dave works 8
hours/day for two weeks on task #2. The total duration of the project
should be 2 weeks.
Unfortunately, Project doesn't understand my wish for a part-time
task. The unit for task 2 is set to 100%, so the entire task is
scheduled after task 1. If I set it to 87.5%, then the second week
John is scheduled to work 7 hours/day which is not correct.
Does anyone know how to solve this problem? I can set a task that John
has a repetitive task for 1 week for 1 hour/day, but I don't like
repetitive tasks.
I put a sample project for this scenario on my website, so please
download http://home.ict.nl/~ramklein/Photos/SampleProject.mpp