Jack
I would like to schedule a task for 4 hours on Monday and 2 hours on
Wednesday for the duration of a project. Is there a way to do this in
project. I have tried setting the hours in the Task Sheet but project keeps
moving the work over the duration and spreading the hours over the week.
jack
Wednesday for the duration of a project. Is there a way to do this in
project. I have tried setting the hours in the Task Sheet but project keeps
moving the work over the duration and spreading the hours over the week.