carey
I come from the Primavera world of scheduling applications. Whereas, in P3
there exist a report that can be generated to show the scheduler if there are
problems with the schedule. These items include: which activities are
constrained; which activities are milestones; loops in the logic; open ended
activities; update status of activities that are out of sequence (ie, started
after the data date; started on the data date, etc); number of activities in
the project; and various other items.
I am unable to find nor generate a report of this sort. I would appreciate
your assistance because doing the schedule critique is very laborious in MSP
2003. Your help to find or create a report of this sort would be greatly
speed up my critique time.
TIA
there exist a report that can be generated to show the scheduler if there are
problems with the schedule. These items include: which activities are
constrained; which activities are milestones; loops in the logic; open ended
activities; update status of activities that are out of sequence (ie, started
after the data date; started on the data date, etc); number of activities in
the project; and various other items.
I am unable to find nor generate a report of this sort. I would appreciate
your assistance because doing the schedule critique is very laborious in MSP
2003. Your help to find or create a report of this sort would be greatly
speed up my critique time.
TIA